Installation Method of Inclined Pipe Sedimentation Tank

Oct 08,2019

Installation Method of Inclined Pipe Sedimentation Tank

The conventional installation method of inclined tube sedimentation tank is as follows:

1. Installation of sludge discharge pipe at bottom of inclined pipe sedimentation tank

The installation sequence of inclined pipe sedimentation tank generally starts at the bottom, and the installation of the bottom sludge discharge pipeline system is completed first. The installation master should ensure that the hole of the sludge discharge pipeline meets the design requirements and is fixed firmly. After the inspection is correct, the next procedure is entered.

II. Installation of Inclined Pipe Packing Bracket

According to the construction plan of filler bracket installation in inclined pipe sedimentation tank, the filler bracket is first installed in place, and all welding joints are checked to be reliable, the bracket strength is enough to bear the weight of filler, and the anti-corrosion treatment is completed on the surface of the bracket.

3. Complete filler ironing of inclined pipe

Each oblique filler is packed as a separate ironing unit according to the ironing method of oblique filler. One unit is 1 m2 after ironing. After ironing, it is stacked neatly on the site.

IV. Installation of Inclined Pipe Packing Pool

The filler unit after hot bonding is assembled from left to right on the upper part of the filler support. Always keep the 60 degree angle unchanged, when assembling, it should be properly pressed. If the size is not right when assembling to the right side, it needs to be assembled according to the size after ironing with the filler of the oblique tube of the loose pieces until all are in place.

Fixed upper packing of inclined tube sedimentation tank

Because the proportion of inclined pipe filler is 0.92, slightly less than water, when the inclined pipe filler is assembled in the tank, it needs to be reinforced by 10 mm round steel pulled from left to right above the filler (two round steel are required to pass through the upper part of each unit filler). The two ends of the round steel are fixed reliably on the wall of the sedimentation tank. After installing the round steel, the inclined pipe filler can be well prevented from occurring in the initial use. The phenomenon of loosening and floating.

6. Operation and commissioning of inclined tube sedimentation tank

(1) Check whether the inlet water is uniform or not, so as not to impact the inclined pipe sedimentation tank and affect the sedimentation effect;

(2) Adjust the height and level of the outlet weir trough to a suitable level to maintain uniform outlet water;

After the above construction process, the installation of filler in inclined pipe sedimentation tank has been completed.

After the inclined pipe sedimentation tank is put into operation normally, it is necessary to determine the sludge discharge period according to the suspended matter concentration in the influent, pay attention to timely sludge discharge, and ensure that the inclined pipe sedimentation tank always keeps good operation status and satisfactory effluent quality.


Send Inquiry

Contact Us

  • Add:No.26 Chuangye Road Heqiao Town Yixing City Jiangsu China
  • Tel:+86-510-87877760
  • Fax:+86-510-87877760
  • Ph:+8617751526380
  • E-mail:sales@khnwatertreatment.com

QR Code

Copyright © Wuxi Deiichen Machinery Pty.,Ltd. All Rights Reserved.