Automatic dosing equipment installation
Nov 09,2021
①The control cabinet is installed on a metal wide frame about 50-250mm high from the ground .
②The control cabinet should be installed in a room that complies with Article 4.5
③The distance from the dosing point to the sampling point is about 8-10 meters, which is suitable for fast adjustment systems. For large lag adjustment systems, the distance from dosing to the sampling point can be unlimited, but it may be suitable.
④ rapid adjustment of a sensor system monitors ( or whole ) should be close to the sampling point, the sampling tube over about 5--8mm, a length of about 2--4 meters, large retardation of the entry system is not critical
https://www.khnwatertreatment.com/